Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent iSQI IREB_CPRE_FL Exam Dumps

 

Prepare for the iSQI IREB Certified Professional for Requirements Engineering – Foundation Level exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the iSQI IREB_CPRE_FL exam and achieve success.

The questions for IREB_CPRE_FL were last updated on May 1, 2025.
  • Viewing page 1 out of 9 pages.
  • Viewing questions 1-5 out of 45 questions
Get All 45 Questions & Answers
Question No. 1

Requirements must be checked in terms of content, documentation and agreement. Indicate with regard to this whether each statement is true or false. (2 Points)

Show Answer Hide Answer
Correct Answer: B, D, F, H

Question No. 2

A new system for monitoring vital functions of patients is to be developed. The system is to be used in intensive care. The usability of the system is especially critical, primarily because the nursing staff must correctly interpret the information indicated by the system and do so under great time pressure. Which two techniques are best suited to identifying the user requirements? (2 Points)

Show Answer Hide Answer
Correct Answer: A, D

Question No. 3

The activity diagram below shows a simplified order processing procedure. Which of the following statements is correct for this flow? (2 Points)

Show Answer Hide Answer
Correct Answer: C

Question No. 4

As part of the "UniKasso" project, the "CRETIL" company is standardising the payment methods for all customers. The requirements specification has been created and the first release is currently being implemented. This week, the management has decided to include the implementation of the "credit card" mode of payment in the first release and to shift the "direct debit" mode of payment to the second release. The test manager receives the order to adjust the test planning accordingly. Which particular characteristic of the requirements will facilitate the work of the test manager significantly in this respect? (1 Point)

Show Answer Hide Answer
Correct Answer: E

Question No. 5

Requirements elicitation: Your company has received a customer contract to develop a system for the scheduling of the customer's delivery vans. It is your task to identify the requirements for this scheduling system. You have arranged appointments for interviews with three key members of the customer's staff, and are now preparing interview questions. Which of the questions below are appropriate interview questions for the requirements elicitation? (2 Points)

Show Answer Hide Answer
Correct Answer: C