Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-SP Exam Dumps

 

Prepare for the PMI Scheduling Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-SP exam and achieve success.

The questions for PMI-SP were last updated on Apr 22, 2026.
  • Viewing page 1 out of 65 pages.
  • Viewing questions 1-5 out of 326 questions
Get All 326 Questions & Answers
Question No. 1

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Show Answer Hide Answer
Correct Answer: C

The schedule performance index is found by dividing the earned value by the planned value. For

Holly's project, it would be as follows:

SPI = EV/PV

= (0.85*9,850,400)/(0.95*9,850,400)

=8,372,840/9,357,880

=0.89

Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in

trend analysis to predict future performance.

SPI is the ratio of earned value to planned value. The SPI is calculated based on the following

formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The SPI value of 1 indicates that the project is right on target.

Answer option D is incorrect. Ten percent is not a valid calculation for this question.

Answer option B is incorrect. 0.98 is the cost performance index.

Answer option A is incorrect. 1.07 is the to-complete performance index based on the BAC.


Question No. 2

You work as the project manager for Blue Well Inc. You are working with your project team to schedule the days the project work will take place. You have created a project network diagram as shown in the figure:

Based on this diagram, find out the earliest day on which Activity G can be started.

Show Answer Hide Answer
Correct Answer: D

The earliest Activity G can start is Day 17. This is because activities A, D, C, and F must

all be completed before Activity G can start.

Answer option A is incorrect. Day 13 does not account for Activity F since Activity F is also a

predecessor to Activity G.

Answer option C is incorrect. Day 22 is the earliest Activity G can finish.

Answer option B is incorrect. Day 7 is not a valid answer.


Question No. 3

In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?

Show Answer Hide Answer
Correct Answer: D

The various techniques of group decision making are as follows:

Unanimity: In this technique, everyone agrees on a single course of action.

Majority: In this technique, more than 50% of the members of the group support the decisions.

Plurality: In this technique, the largest block in a group decides even if a bulk is not achieved.

Dictatorship: In this technique, one individual makes the decision for the group.


Question No. 4

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

Show Answer Hide Answer
Correct Answer: B

Soft logic can be completed in any order without affecting the outcome of the deliverables.

Soft logic is also known as preferential logic, preferred logic, and discretionary dependency. It is

defined on the basis of knowledge of best practices and standard procedures for the particular

application area. Soft logic is defined by the project management team based on well-

known practices in a specific desired sequence.

Answer options A, D, and C are incorrect. These are not valid definitions of soft logic.


Question No. 5

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

Show Answer Hide Answer
Correct Answer: B

The cost variance for the project is -$51,000. You can find the cost variance by using the formula earned value minus planned value. In this instance, it is: CV = EV - AC = (0.60* 2,456,900) - 1,525,140 = -51,000 Answer option C is incorrect. -$85,000 is the project's variance at completion. Answer option A is incorrect. $122,845 is the project's schedule variance. Answer option D is incorrect. There is a cost variance on this project of -$51,000.


Unlock All Questions for PMI PMI-SP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 326 Questions & Answers