QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the SAP C_ACTIVATE22 exam and achieve success.
You are defining the testing strategy for your project.What would you include in a Scope of Integration test?
A is correct because the functionality of end-to-end business processes is one of the things that you would include in a Scope of Integration test. The integration test is a test that verifies that the solution works as expected across different systems and interfaces, and supports the complete business scenarios that are relevant for the customer. Verified :
: SAP Activate Project Management Certification Guide, page 120
What activity do you perform during the daily stand-up meeting?
C is correct because reporting showstoppers is one of the activities that you perform during the daily stand-up meeting. A showstopper is an issue or impediment that prevents the team from completing their sprint goal or user story. The scrum master is responsible for resolving or escalating the showstoppers as soon as possible. Verified :
: SAP Activate Project Management Certification Guide, page 115
How do you set up Scrum teams?Note: There are 2 correct answers to this question.
A is correct because based on end-to-end processes like order-to-cash is one of the ways to set up Scrum teams. This way, the Scrum teams are organized around the business value streams that they support, and they have a clear understanding of the customer needs and expectations. This also helps to reduce dependencies and handovers between teams, and to optimize the flow of work.
C is correct because as a cross-functional team covering multiple functions, like configuration, data loads, and testing is one of the ways to set up Scrum teams. This way, the Scrum teams have all the skills and competencies that they need to deliver a complete and working product increment in each Sprint. This also helps to increase collaboration and communication within the team, and to foster a sense of ownership and accountability.
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
C is correct because in an Agile approach, the planning is done iteratively and incrementally, so the minimum requirement at the beginning of the Realize phase is to have sprint planning and sprint durations defined for the first 2 to 3 sprints. Verified :
:SAP Activate Project Management Certification Guide, page 117