During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization. What is the most likely planning anti-pattern causing this sudden impediment?
The most likely planning anti-pattern in this scenario is when prioritization by Product Management is performed autonomously rather than collaboratively. This is evident from the issue raised during the scrum of scrums, where a Product Manager presents a priority wish list that does not align with the already established Feature prioritization.
To prevent such anti-patterns, SAFe recommends that:
Product Management works closely with Business Owners and other stakeholders during the Continuous Exploration process to align on vision, roadmap, and backlogs.
By following these practices, SAFe ensures that prioritization is a collective effort, reflecting the needs and inputs of all relevant parties, and supporting the successful execution of PI Planning.